A private committee has been formed with the intent to remodel or construct a new stadium that will open for play in August 2010. This project is required in order to create a safer environment both for the fans and the players. It is also a priority to make our stadium more handicap accessible. The new stadium will sit at the current location, and will be used for all levels of football from Varsity to Little Leopards, as well as band shows, soccer games, and baseball/softball practice. It is our intent to complete the new stadium in two phases, and we will need support from the community in order to reach our goals.
- Bleacher Delivery – April 2010
- Bleacher Installation – (Visitor) April 2010
- Bleacher Installation – (Home) May 2010
- Locker Room, Concessions, Restroom Construction, April/July 2010
- Lighting Installation – June 2010
- Turf Installation – July 2010
- Scoreboard, Paving, Fencing and Misc. Installation – July/August 2010
FIRST HOME GAME! SEPTEMBER 10, 2010!
The stadium committee is continuing to raise funds and would appreciate the
continued support of our community. The goal of the stadium committee is
to raise 100% of the funds needed and complete 100% of the project.
Initially, the committee believed the project would have to be completed in
phases over several years. Due to the overwhelming support of the
community and generous gifts of time and money from corporate sponsors,
the committee is committed to completing the entire project in the next eight
months! This is an ambitious undertaking, but the drive and desire to
succeed for the committee is similar to that shown by our Leopard Football
teams.
Please e-mail with questions, concerns, or comments at: louisvilleleopardstadium@yahoo.com
|